14th Avenue Road & Utility Improvements Phase 2 – Grand Street to Cade Barr Street

View at street level along 14th avenue
Type
Engineering
Address
14th Avenue (Grand Street to Cade Barr Street)

Traffic Update - April 22, 2024

The contractor is continuing to work diligently along 14th Avenue and to accommodate the increased activity, 14th Avenue will be closed, with local traffic maintained, from Grand Street to Knight Avenue during daytime working hours. 

Local residents, transit and emergency services will continue to have access. The area is relatively straightforward to detour however, motorists are reminded to respect the speed limit when using their alternate routes. Thank you for your continued patience and cooperation.

 

Project Update April 25, 2024

The contractor is currently completing final grading in preparation for the baselift of asphalt and wrapping up storm works. Watermain construction has begun and the contractor will be working some Saturdays to remain on schedule. 

What's happening

The City is moving ahead with a 3-phase improvement program for 14th Avenue from Hurd Street to Cade Barr Street. After successful completion of Phase 1 from Hurd Street to Tanager Street, in October 2022, construction is scheduled to start on Phase 2 from Grand Street to Cade Barr Street in November 2023.

Phase 2 will have a similar road cross sections as Phase 1.

Proposed Work Includes:

  • Watermain and drainage upgrades
  • Multi-use pathway (south side)
  • Improved sidewalk and connectors (north side)
  • Curb bulges, parking pockets and enhanced boulevard improvements
  • Pavement, road markings and intersection improvements at Caribou Street
  • Street lighting and buried conduit installation 

During construction, every effort will be made to minimize the inconvenience to residents however, with work of this nature, some inconvenience will be unavoidable and we ask for your patience and cooperation during this time. 14th Avenue will remain open with minimum single lane alternating traffic throughout construction.

A Notice to Residents Letter was sent October 18, 2023 [PDF/213KB] to affected residents.

Construction Schedule

Construction is expected to be completed over a 6-month period.

PhaseTime Period
Construction*November 2023- May 2024

*Weather permitting

Prime Contractor

B&B Heavy Civil Construction Ltd.
info@bbcontracting.com
604-862-4981

After-Hours Contact

See the yellow Public Works contact card near top of this page on the left side