Updated December 19, 2024 – This project is complete.
What happened
On June 24th, 2022 City staff released a Request for Proposal for the Construction of the Gaudin Creek Community Detention Pond. The project was to complete the construction of a new community detention facility and associated creek channel, downstream of the existing detention facility.
On August 15th council approved a budget increase and awarded the contract to MAREX Constructors Ltd. The Notice to Proceed has been issued, the contractor has submitted their documents and the Contract has been executed. After a pre-construction meeting in August, MAREX mobilized on to the site in September.
A Letter to Residents [PDF/452KB] and a Wildlife Attractants Letter [PDF/391KB] was sent to residents on June 23, 2023.
Site photos October 2022

The completed work included
- Roadway excavation
- Drainage improvements
- New community drainage detention facility
- Pedestrian trail and fencing
- Environmental enhancements
The Contractor utilized two site access points, Hutton Place cul-de-sac, as well as Nottman Street at Dalke Avenue. Project signs were posted at each entrance. Additional traffic control aided with material deliveries and a staging/laydown area. A Notice to Residents letter was distributed to the adjacent and directly impacted residents.

Notice to residents
- Notice to Residents Letter – August 31, 2022 [PDF/313KB]
- Notice to Residents Letter – June, 2023 [PDF/452KB]
- Wildlife Attractants Letter – June, 2023 [PDF/391KB]
Prime Contractor
MAREX Constructors
Brian Phillips, Site Superintendent
604-819-9808