Penitentiary Lift Station Upgrade

Sub-Menu

 

 

Penitentiary Lift Station Upgrade – Mission Medium Security Institution Grounds

 

What’s Happening

This project involves constructing a new sanitary lift (pump) station to replace the existing facility as it has reached the end of its design life. The sewer catchment of this station includes the Mission Institution and is generally bordered by Dewdney Trunk Road (west), Cherry Avenue (south) and east of Stave Lake Street.

Construction Schedule

Construction will be performed in two mobilizations:

March 27 – June 16, 2023 Station Construction

October 9-12, 2023 Generator Installation

 

After-Hours Contact

Public Works
Ph: 604-820-3761

 

Project Contacts

Rob Racine,
Project Manager,
rracine@mission.ca