Nelson Street Improvements

Sub-Menu

What’s happening

Nelson Street and Galliford Street are undergoing improvements between between Kenny Avenue and Grove Avenue.

These upgrades will update infrastructure and improve safety for all users located along this corridor. Work includes new curbs, medians, left turn lanes, sidewalks, pathways, boulevard trees, lighting, signage, and a full complement of services including fire hydrants for improved fire protection.

Timeline

Stage 1:

  • Base asphalt on Nelson Street between Kenney Avenue and Bench Avenue are scheduled for this Spring, weather permitting; and
  • Substantial Completion of road works on Nelson Street between Kenney Avenue and Bench Avenue are scheduled for early Summer 2021, weather permitting.

Stage 2:

  • Pipe installations and base asphalt on Nelson Street between Bench Avenue and Grove Avenue including Galliford Street are scheduled to complete this Spring, weather permitting;
  • Base asphalt on Nelson Street between Bench Avenue and Grove Avenue including Galliford Street are scheduled to complete late Summer 2021 weather permitting; and
  • Substantial Completion of roadworks on Nelson Street between Bench Avenue and Grove Avenue including Galliford Street are scheduled for late Fall 2021, weather permitting.

What to expect

During the course of these works you can expect traffic delays, road closures, gravel surfaces, compaction resulting in vibrations felt in the home, and general construction activity including heavy equipment and dump trucks. Every effort will be made to keep the inconvenience to the residents to a minimum.  You patience and understanding while these works complete is very much appreciated.

Project Contact

Jay Jackman 
Manager of Development Engineering, Projects & Design
604-820-3745